PERIOD OF ACTION ON PROCUREMENT ACTIVITIES
(EARLIEST POSSIBLE TIME)
|
STAGE |
ACTIVITIES |
DEADLINE |
GOODS |
INFRASRUCTURE PROJECTS |
CONSULTING SERVICES |
|
1 |
Advertisement/ Posting of Invitation to Bid/ Request for Expression of Interest |
7cd |
7cd |
7cd |
|
|
2 |
Eligibility Check (and Short Listing, in case of Consulting Services) |
Refer to Stage 5 |
Refer to Stage 5 |
3cd (1 cd for eligibility, 1 cd for short listing, and 1 cd for notice |
|
|
3 |
Issuance and Availability of Bidding Documents |
From 1st day of Stage 1 until Stage 5 |
|||
|
4 |
Pre-bid Conference |
12 cd before Stage 5 |
1 cd |
1 cd |
1 cd |
|
Request for Clarification |
10 cd before Stage 5 |
||||
|
Supplemental/ Bid Bulletin |
7 cd before Stage 5 |
||||
|
5 |
Submission and Receipt of Bids |
1 cd (includes Opening of Bids and Eligibility Check) |
1 cd (includes Opening of Bids and Eligibility Check) |
1 cd (includes Opening of Bids |
|
|
Submission of Additional Requirements |
3 cd after Stage 5 |
||||
|
6 |
Bid Evaluation |
1 cd |
1 cd |
1 cd + 1 cd for approval of ran king |
|
|
7 |
Notification for Negotiation |
n/a |
n/a |
1 cd |
|
|
8 |
Negotiation |
n/a |
n/a |
1 cd |
|
|
9 |
Post-qualification |
1 cd |
1 cd |
1cd |
|
|
10 |
Approval of Resolution/ Issuance of Notice of Award |
2 cd (1 cd for BAC Resolution and 1 cd for NOA) |
2 cd (1 cd for BAC Resolution and 1 cd for NOA) |
2 cd (1 cd for BAC Resolution and 1 cd for NOA) |
|
|
11 |
Contract Preparation and Signing |
2 cd (1 cd for Contract Preparation and 1 cd for Contract Signing |
2 cd (1 cd for Contract Preparation and 1 cd for Contract Signing |
2 cd (1 cd for Contract Preparation and 1 cd for Contract Signing |
|
|
12 |
Approval of Contract |
1 cd |
1 cd |
1 cd |
Legend:
Cd – Calendar Day(s)
NOA - Notice of Award
BAC – Bids and Awards Committee